One Step integration
One Step Integration assumes all production occurs in an external system, and you want to integrate this into GP so that GP reflects the correct cost of the finished good, and the correct components are removed from inventory. It requires populating the MOHdr table with the Item Number and Quantity to produce. You may also provide a Picklist (if you want to record component consumption that is different than what the Bill of Materials would indicate), and Routing (if you want to indicate actual labor/machine time). If a Picklist and Routing are not provided, MORI will use the Item’s MFG BOM and Primary Routing, and backflush components, labor and machine time.
If a different Routing, or different BOM should be used, those can be provided in the MOHdrOpt table.